PERI, PDC Scaffolding and PSD join forces to deliver a complex recladding project in East London.

PERI, PDC Scaffolding and PSD join forces to deliver a complex recladding project

The solution was a wrap-around consisting of 221 tonnes of PERI UP Flex scaffolding, providing perimeter access to all 16 storeys to facilitate cladding replacement.

Date
08. March 2023

  

The solution was a wrap-around consisting of 221 tonnes of PERI UP Flex scaffolding, providing perimeter access to all 16 storeys to facilitate cladding replacement.

Principal scaffolding designer, PSD Prime Scaffold and Structural Designs Ltd, worked with PERI’s design team throughout the planning phase. Collaborating with the scaffolding supplier early on in the project enabled PSD to get an understanding of the system’s specifications and capabilities, making the installation process on site smoother.

Scaffolding Project Delivery Manager at PERI, Dion Penman, has worked closely with PDC Scaffolding and PSD to deliver the solution. Commenting on the project, Penman said:

“This has been a challenging project given the awkward shape of the building. There are different angles, terraces, and vertical shafts. Nothing is at a right angle. The scaffolding arrangement had to be designed to the absolute millimetre to make it work.”

He added, “PERI UP Flex is ideal for this type of project as the system lends itself to odd shapes. It’s also perfect for cladding projects because the lack of bracing gives the contractor unrestricted access around the scaffold to carry out the work.”

Paul Casey, Managing Director of PDC Scaffolding, explained how flexible system components benefitted the project:

“The reason we’ve used the PERI UP system is because it’s the most versatile system out there. The different deck sizes available in the PERI UP range have been beneficial as we’ve been able to install a deck arrangement that accommodates the shape of the building. In addition to the decks, using components like the console brackets meant that we could get around every part of the building safely, covering all the gaps.”

This is PDC Scaffolding’s fourth project using PERI UP. The scaffolding specialist is investing £2m in the PERI UP system following on from the Payne Road project. This is a continual investment plan to support its recladding and refurbishment projects over the coming years.