Mersey Gateway, Cheshire

Project data

Location: Cheshire, United Kingdom

Purpose: Merseyside’s transport network is undergoing significant improvements. The Mersey Gateway will provide an alternative route, reducing congestion and generating an estimated £61.9m in Gross Added Value by 2030.

Date of Completion: 2017

Requirements

Merseylink Civil Contractors required formwork solutions for the lower pylons and hammerheads.

Customer

Merseylink Civil Contractors (FCC Construcción S.A., Kier Infrastructure and Overseas Limited and Samsung C&T Corporation)

Customer's benefit

Stable work platform amidst high winds

Intricate concrete finishing

Accommodates complex geometries for pier table formwork

Hydraulic ACS enabled crane-independent working operations

 


Are you building a project like this?

Our products and services will make your construction work safer, faster and more efficient.

Call us on 01788 861600 or contact us through our website to discuss your project and find out how we can help.


PERI solution

  • VARIO GT24 formwork with SB Frames and VARIOKIT system were employed to construct the hammerheads. Unlike a typical application, we employed the frames as a platform, creating a unique design for the intricate shape of the hammerhead.
     
  • Once the central hammerhead had been completed, the platform was reused for the pier tables. Sequenced construction avoided the accumulation of vertical forces; ensuring a safer, more manageable process.
     
  • Once the lower pylons and hammerheads had been completed, the central pier table and three different-sized pylons were constructed.
     
  • With the south pylon rising to 125m high, the ACS and custom formwork platforms were on hand to combat the challenging wind speeds.