Haribo Production Facility
Castleford,
United Kingdom
30,700 sqm of space.
Large 74m2 tables.
To construct shear walls, in-situ stairs and suspended slabs.
Slab pour sizes averaged 1047m² with a concrete volume of 523m³.
Location
Main Application
Buildings
The Project
MULTIPROP, with the easily adjustable collar used to support the construction of the high level soffits
Each MULTIPROP has an integrated tape measure which can be pre-set before erection saving time-consuming measuring and re-adjustments
Crane moving complete MULTIPROP Table of 72m2, weighting 4.5 tonnes from block level 2 to the roof. The tables were pre-assembled on castors for easy re-location between floors and areas
MULTIPROP, with the easily adjustable collar used to support the construction of the high level soffits
Each MULTIPROP has an integrated tape measure which can be pre-set before erection saving time-consuming measuring and re-adjustments
Crane moving complete MULTIPROP Table of 72m2, weighting 4.5 tonnes from block level 2 to the roof. The tables were pre-assembled on castors for easy re-location between floors and areas
Project Information
“PERI’s technical office has been terrific from the very offset and has provided continuous dialogue and regular site visits during the length of the project. This helped identify possible design problems and eliminate any issues later on, meaning that minimal revisions were required when it came to using the equipment on site."
Paul McGarry
Construction Manager